Council to vote Nov. 17 on a $27.5 million contract to build the new recreation center at the old Stewart Creek Elementary

Steele & Freeman's guaranteed maximum price covers renovating about 30,600 square feet of the former school and adding a two-court gym with an elevated track, with completion possible by September 2027.

Quincy Underwood· AI-assisted, edited by Jake Team

November 10, 20262 min read

Recreation Center Build - illustration, Jake Team LLC

The Colony City Council is set to award the construction contract for the city's new recreation center next week, at a guaranteed maximum price of $27,476,822.

Steele & Freeman Inc., the construction manager the city picked from a field of 13 firms to work alongside designer Huitt-Zollars, submitted the price. The council takes it up as a regular agenda item at its 6:30 p.m. meeting Tuesday, Nov. 17, at City Hall, 6053 Main St. The Community Development Corporation would pay for it with bond money it has issued.

The center will go into the former Stewart Creek Elementary and replace the current recreation center, which the parks department's memo says no longer meets the community's needs.

Plans call for renovating about 30,647 square feet inside the school for fitness areas, rooms that can be rented or used for classes, a gaming and esports space, offices, storage and a lobby. A new gymnasium wing would hold two full-size courts and an elevated track for runners, plus storage for equipment. The memo puts the addition at a little more than 22,000 square feet.

The contractor estimates about 15 months of construction but told the city the job could be done by September 2027 barring major delays.

Staff wrote that they have found about $1.8 million in possible value engineering savings within the guaranteed price, and that any savings would come back to the city when the project closes out.

A state accessibility filing the city made in October put the project at $26 million.

On the same agenda, the consent items include up to $480,000 for LED field lights and poles at B.B. Owen Park, also paid by the Community Development Corporation, and $118,503 for fire department uniforms. Council will also canvass the Nov. 3 election, swear in the winners of Places 3, 5 and 6 and formally order the Place 4 runoff.

Sources

thecolony.granicus.com

d3n9y02raazwpg.cloudfront.net

Share

Quincy Underwood· AI-assisted, edited by Jake Team

Quincy Underwood covers The Colony city hall, the council, and county government.